Property managers and associations

How much does it cost to repaint a condominium or commercial building in South Florida?

Last updated · Atrium Construction, Boca Raton, Florida

Building-scale repainting in South Florida is priced by gross exterior wall area, not floor area or unit count. Atrium's recent figures: an eleven-building, 264-unit community priced at $459,000, about $1,739 per unit; a six-story occupied mixed-use building in Delray Beach at $405,007; a nine-building tilt-up warehouse portfolio completed in 2024 at $987,342, about $109,700 per building; and seven warehouses with three monument signs priced at $1,034,190. Draws run 40% at signing, 30% at midpoint and 30% at completion, per building, with lien releases.

Typical project range: $50,000 – $1,034,190 from a single association or commercial building to a seven-warehouse portfolio; four real projects between $405,007 and $1,034,190 are itemized on this page.

Four real building-scale projects

ProjectScaleValuePer buildingStatus
Garden-style community11 buildings, 264 units$459,000$41,727 · $1,739 per unitPriced
Mixed-use building, Delray Beach6 stories, occupied, swing stage$405,007—Priced 2026
Logistics center9 tilt-up warehouses$987,342~$109,700Completed 2024
Industrial park7 warehouses, 3 monument signs$1,034,190~$147,700Priced 2026

What sets the price

DriverEffect
Gross wall areaThe base quantity: painted perimeter × parapet or eave height, per building, openings not deducted
Height and accessBoom lifts to about three stories; swing stage above that — slower, and it needs roof anchorage and overhead pedestrian protection
Coating age and conditionAn old chalking coating needs more cleaning and a conditioner primer; a failed one needs removal
Stucco, concrete and sealantRepairs beyond ½ inch, spall repair and full sealant replacement are separate lines from a sounding survey
MetalOverhead doors, railings, ladders and canopies by count and area, in Sher-Cryl enamel
OccupancyBalcony access, resident notices, daily cleanup and overnight equipment storage on occupied buildings
Contract positionA direct contract with an owner or association carries supervision and general conditions that a bid to a general contractor does not
SpecificationA named textured coating priced as an approved equal — on a seven-building portfolio, a $109,000 difference between two compliant Sherwin-Williams products

Where the money goes on a warehouse portfolio

The lines on an Atrium commercial proposal, in the order they appear:

LineUnit
Wash, prep and repaint — laborhours, from wall area
Sherwin-Williams materials including sundriesunits, about one per 160 ft² of wall
Stucco or concrete panel repairshours
Sealant replacement, spot treatmenteach
Repaint metal railings, doors, ladders, canopieshours
Equipment: boom lifts, container, dumpster, sanitationper building
Supervision and project managementabout 10% of production hours
Daily cleanup and overnight storagehours, occupied buildings

Terms

TermStandard
Draws40% at signing or commencement · 30% at 50% · 30% at 100%, per building
PaymentNet 14 days
Lien releasesConditional with each draw; final with final payment
SequencingGroups of three buildings; next group commences before the previous closes
DurationFour to six weeks per warehouse; nine buildings April 17 to July 24
Validity90 days, with a material escalation clause above a 5% Sherwin-Williams price movement
Warranty1 year workmanship from each certificate of completion; 7-year manufacturer warranty assigned

Sources

  • Atrium proposal, eleven buildings and 264 units — $459,000 exterior repaint
  • Atrium proposal and basis of estimate, six-story occupied mixed-use building, Delray Beach, 2026 — $405,007, repricing a 2015 lump sum of $230,000
  • Atrium contract records, nine tilt-up warehouses, 2024 — $987,341.96, April to July, groups of three
  • Atrium proposal, seven warehouses and three monument signs, 2026 — $1,034,190, one proposal per building

Related questions

How much per unit does a condominium repaint cost?
The eleven-building, 264-unit community priced at $459,000 works out to $1,739 per unit or $41,727 per building. Per-unit is a useful number for a board's budgeting, but it is an output of the price, not the input: the price comes from wall area, height and access. Two communities with the same unit count can differ by half if one is two stories on lifts and the other is six on swing stages.
Why do warehouse repaints cost more per building than condominium buildings?
Wall area. A tilt-up distribution building has 30-foot parapets and a perimeter of a thousand feet or more, so a single warehouse can carry as much wall as several garden-style condominium buildings. Nine warehouses at $987,342 averaged about $109,700 each; eleven condominium buildings at $459,000 averaged $41,727.
How is a building priced?
Painted perimeter times parapet height gives gross wall area, openings not deducted. Labor is production work by the square foot; material is about one unit — a gallon of finish, half a gallon of primer and sundries — per 160 square feet of wall. Sealant spot treatment, stucco or concrete repairs beyond half an inch, metal railings and doors, and equipment (lifts or swing stage, container, dumpster) are their own lines. On a warehouse portfolio every 100 feet of perimeter error moves the price by roughly $16,000, which is why perimeter is measured, not assumed.
What does the draw schedule look like?
40% at signing or at commencement of that building, 30% at 50% completion, 30% at 100% completion. Net 14 days. Each building is contracted, invoiced and closed out on its own, with a conditional lien release at every draw and a final release on final payment. On a portfolio, buildings start in groups of three so an invoice lands roughly every two weeks.
What about a building that was painted ten years ago for much less?
A six-story building painted in 2015 for a lump sum of $230,000 was repriced in 2026 at $405,007, and the basis-of-estimate document shows why: the area was measured this time, cost escalation since 2015 is about 1.44 times, the coating is ten years older and needs more prep, and the contract is now direct with the association rather than a subcontract to a general contractor. Every reprice gets that document, so the board does not have to reverse-engineer the arithmetic.